Qld plans green energy hub amid coal plant delay

March 09, 2023 10:16 AM AEDT | By AAPNEWS
 Qld plans green energy hub amid coal plant delay
Image source: AAPNEWS

Queensland is calling for community input on a renewable energy hub near Ipswich after a major coal power plant near Gladstone delayed its return to full capacity until next year.

State-owned CleanCo Queensland has called for input from the community to assess and progress a hub at Swanbank near Ipswich that includes solar power, a 250MW battery and hydrogen.

The hub will be integrated with CleanCo's Swanbank E gas-fired power station, which already has a capacity of 385MW.

CleanCo chief executive Tom Metcalfe says the project will have an "authentic co-design" which includes site restoration, such as an ecological corridor and recreational spaces.

"We will not just be asking: what do you think? but rather, what does the community need and value?' and how can we collaborate to create the masterplan together and build enduring partnerships?" he said in a statement on Thursday.

"And we are committed to delivering genuine outcomes from this process.

Queensland Energy Minister Mick de Brenni said the project was part of a broader plan to meet a target of 70 per cent of energy consumed being provided by renewable sources by 2032, and 80 per cent by 2035.

The announcement comes a day after public-owned generator CS Energy announced a major coal-fired power station won't be fully operational until January next year.

The company's 1540MW Callide power station near Biloela, which meets roughly 30 per cent of the state's electricity demand, has not run at capacity since May 2021.

That was when the plant's C4 generation unit was destroyed in an explosion, while the C3 unit was taken offline after structure failure caused a collapse of its cooling tower in September.

The C3 unit was due to return to full capacity by September 30, while the C4 unit was due to be fully operational by October 31. 

However, CS said it would delay the return of both units to full capacity so it can rebuild the cooling towers of both units.

The return of C3 had been postponed by six months to December 31, while C4 has been delayed another eight months, meaning Callide won't have run at full strength for two years and eight months.

The company insists the delay is "not unusual" and depends on issues identified during major repair and maintenance.

The announcement reportedly triggered a leap in wholesale electricity prices bringing fresh uncertainty about whether those prices would be passed onto household consumers and businesses.

Mr de Brenni has previously stressed the state has enough generation capacity to meet demand with Callide running at reduced capacity.


Disclaimer

The content, including but not limited to any articles, news, quotes, information, data, text, reports, ratings, opinions, images, photos, graphics, graphs, charts, animations and video (Content) is a service of Kalkine Media Pty Ltd (“Kalkine Media, we or us”), ACN 629 651 672 and is available for personal and non-commercial use only. The principal purpose of the Content is to educate and inform. The Content does not contain or imply any recommendation or opinion intended to influence your financial decisions and must not be relied upon by you as such. Some of the Content on this website may be sponsored/non-sponsored, as applicable, but is NOT a solicitation or recommendation to buy, sell or hold the stocks of the company(s) or engage in any investment activity under discussion. Kalkine Media is neither licensed nor qualified to provide investment advice through this platform. Users should make their own enquiries about any investments and Kalkine Media strongly suggests the users to seek advice from a financial adviser, stockbroker or other professional (including taxation and legal advice), as necessary.
The content published on Kalkine Media also includes feeds sourced from third-party providers. Kalkine does not assert any ownership rights over the content provided by these third-party sources. The inclusion of such feeds on the Website is for informational purposes only. Kalkine does not guarantee the accuracy, completeness, or reliability of the content obtained from third-party feeds. Furthermore, Kalkine Media shall not be held liable for any errors, omissions, or inaccuracies in the content obtained from third-party feeds, nor for any damages or losses arising from the use of such content.
Kalkine Media hereby disclaims any and all the liabilities to any user for any direct, indirect, implied, punitive, special, incidental or other consequential damages arising from any use of the Content on this website, which is provided without warranties. The views expressed in the Content by the guests, if any, are their own and do not necessarily represent the views or opinions of Kalkine Media. Some of the images/music that may be used on this website are copyrighted to their respective owner(s). Kalkine Media does not claim ownership of any of the pictures displayed/music used on this website unless stated otherwise. The images/music that may be used on this website are taken from various sources on the internet, including paid subscriptions or are believed to be in public domain. We have made reasonable efforts to accredit the source wherever it was indicated as or found to be necessary.
This disclaimer is subject to change without notice. Users are advised to review this disclaimer periodically for any updates or modifications.


AU_advertise

Advertise your brand on Kalkine Media

Sponsored Articles


Investing Ideas

Previous Next
We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it.