Xinhua Silk Road: AC-DC conversion of transmission lines helps resolve power demand and grid upgrading dilemma in E. China

April 30, 2024 02:36 PM AEST | By Cision
 Xinhua Silk Road: AC-DC conversion of transmission lines helps resolve power demand and grid upgrading dilemma in E. China
Image source: Kalkine Media

BEIJING, April 30, 2024 /PRNewswire/ -- Yangzhou-Zhenjiang DC power transmission project, the first project to convert in-operation AC transmission lines to DC ones in China, was put into service in east China's Jiangsu Province on Sunday.

Without changing the main structure of the cross-Yangtze River transmission towers, State Grid Jiangsu Electric Power Co., Ltd. upgraded transmission lines between the two cities at different sides of the river to improve transmission capacity of existing grids.

As a reproducible example, the project means much for areas with a large population but limited space for new grids construction as related AC-DC conversion technologies can solve long-distance power transmission problems between regional power grids and save much costs, said Chen Songtao, planning and management director with construction department of State Grid Jiangsu Electric Power Co., Ltd.

Currently, power transmission to south Jiangsu from north Jiangsu dotted by new energy power projects relies mainly on six cross-Yangtze River transmission corridors. But increasing power transmission demand and stricter Yangtze River ecological protection make new corridor building less likely and improving transmission capacity of existing corridors is more imperative now.

Compared with AC power transmission lines, DC ones of same voltage have greater transmission capacity and lower transmission loss and through AC-DC conversion, the Yangzhou-Zhenjiang transmission lines now boast a transmission capacity of 1.2 million kW, introduced Chen.

Apart from capacity expansion, AC-DC conversion of transmission lines have multiple advantages such as high reliance and economic efficiency. Taking the cross-Yangtze River section as an example, its construction period was 5-6 months shorter than that of building new transmission lines and related investment dropped by nearly 60 million yuan, added Chen.

Using smart robots to achieve highly efficient and green construction, State Grid Jiangsu Electric Power saw related efficiency much improved than traditional manual construction. Xu Huaiyu, vice chief engineer of the project said a batch of engineering resolutions for long-distance transmission line change and nine innovation achievements have been developed independently by the company to facilitate the following construction.

After completion of phase II and III of the project, its transmission capacity is likely to reach 3.60 million kW and further satisfy the power transmission demand in Jiangsu.

Original link: https://en.imsilkroad.com/p/339979.html


Disclaimer

The content, including but not limited to any articles, news, quotes, information, data, text, reports, ratings, opinions, images, photos, graphics, graphs, charts, animations and video (Content) is a service of Kalkine Media Pty Ltd (“Kalkine Media, we or us”), ACN 629 651 672 and is available for personal and non-commercial use only. The principal purpose of the Content is to educate and inform. The Content does not contain or imply any recommendation or opinion intended to influence your financial decisions and must not be relied upon by you as such. Some of the Content on this website may be sponsored/non-sponsored, as applicable, but is NOT a solicitation or recommendation to buy, sell or hold the stocks of the company(s) or engage in any investment activity under discussion. Kalkine Media is neither licensed nor qualified to provide investment advice through this platform. Users should make their own enquiries about any investments and Kalkine Media strongly suggests the users to seek advice from a financial adviser, stockbroker or other professional (including taxation and legal advice), as necessary.
The content published on Kalkine Media also includes feeds sourced from third-party providers. Kalkine does not assert any ownership rights over the content provided by these third-party sources. The inclusion of such feeds on the Website is for informational purposes only. Kalkine does not guarantee the accuracy, completeness, or reliability of the content obtained from third-party feeds. Furthermore, Kalkine Media shall not be held liable for any errors, omissions, or inaccuracies in the content obtained from third-party feeds, nor for any damages or losses arising from the use of such content.
Kalkine Media hereby disclaims any and all the liabilities to any user for any direct, indirect, implied, punitive, special, incidental or other consequential damages arising from any use of the Content on this website, which is provided without warranties. The views expressed in the Content by the guests, if any, are their own and do not necessarily represent the views or opinions of Kalkine Media. Some of the images/music that may be used on this website are copyrighted to their respective owner(s). Kalkine Media does not claim ownership of any of the pictures displayed/music used on this website unless stated otherwise. The images/music that may be used on this website are taken from various sources on the internet, including paid subscriptions or are believed to be in public domain. We have made reasonable efforts to accredit the source wherever it was indicated as or found to be necessary.

This disclaimer is subject to change without notice. Users are advised to review this disclaimer periodically for any updates or modifications.

AU_advertise

Advertise your brand on Kalkine Media

Sponsored Articles


Investing Ideas

Previous Next
We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it.