KUITUN, China, Dec. 12, 2024 /PRNewswire/ -- In the face of biting cold winds, construction of the 220-kilovolt Xiaye Di to Shihezi West π Line project is progressing vigorously. At the site, machinery operates nonstop as workers carry out conductor tensioning and laying operations between towers 70 and 80. After 273 days of relentless work, the dedicated team at State Grid Kuitun Power Supply Company continues to endure harsh weather conditions to ensure the project is completed on schedule. This milestone aims to guarantee safe and stable power grid operations during the peak winter period.

Shihezi City and the Eighth Division of the Xinjiang Production and Construction Corps have focused on resource transformation and large-scale industrial strategies. This key project is crucial for meeting the electricity needs of the Eighth Division, integrating new energy resources, and ensuring the stable operation of the power grid.

Spanning 23.693 kilometers and involving 82 iron towers, the project features a tension ratio of 56%. Construction began on April 10, 2024, with completion and power transmission slated for December. According to Liu Ziyu, the project manager, 92% of the work has been completed, with current efforts focused on wire tightening and accessory installation.

Located in agricultural zones of Shihezi City and Shawan City, the project's route is shaped by restrictions such as farmland boundaries, ecological red lines, and existing infrastructure. These limitations have necessitated intricate planning for tower foundations. "The route's tension ratio of 56% is significantly higher than standard lines due to these complexities," explained Teng Zhipeng, the construction project manager. "We've used 18 different tower types, including angle steel towers, steel pipe poles, and narrow-base towers. The project also includes 37 instances of crossing under 750-kilovolt lines, as well as crossings over 220-kilovolt lines, 10-kilovolt lines, and national highways. Approximately 1.6 kilometers of 10-kilovolt lines have been reconstructed."

Upon completion, the 220-kilovolt line will significantly enhance the regional power network. It will establish a 44.58-kilometer connection between the Shihezi 750-kilovolt Substation and the Shihezi West Substation, as well as an 89.17-kilometer link to the Xiaye Di 220-kilovolt Substation.

The State Grid Kuitun Power Supply Company remains committed to delivering critical infrastructure that drives regional development and ensures energy security.


Disclaimer

The content, including but not limited to any articles, news, quotes, information, data, text, reports, ratings, opinions, images, photos, graphics, graphs, charts, animations and video (Content) is a service of Kalkine Media Pty Ltd (“Kalkine Media, we or us”), ACN 629 651 672 and is available for personal and non-commercial use only. The principal purpose of the Content is to educate and inform. The Content does not contain or imply any recommendation or opinion intended to influence your financial decisions and must not be relied upon by you as such. Some of the Content on this website may be sponsored/non-sponsored, as applicable, but is NOT a solicitation or recommendation to buy, sell or hold the stocks of the company(s) or engage in any investment activity under discussion. Kalkine Media is neither licensed nor qualified to provide investment advice through this platform. Users should make their own enquiries about any investments and Kalkine Media strongly suggests the users to seek advice from a financial adviser, stockbroker or other professional (including taxation and legal advice), as necessary.
The content published on Kalkine Media also includes feeds sourced from third-party providers. Kalkine does not assert any ownership rights over the content provided by these third-party sources. The inclusion of such feeds on the Website is for informational purposes only. Kalkine does not guarantee the accuracy, completeness, or reliability of the content obtained from third-party feeds. Furthermore, Kalkine Media shall not be held liable for any errors, omissions, or inaccuracies in the content obtained from third-party feeds, nor for any damages or losses arising from the use of such content.
Kalkine Media hereby disclaims any and all the liabilities to any user for any direct, indirect, implied, punitive, special, incidental or other consequential damages arising from any use of the Content on this website, which is provided without warranties. The views expressed in the Content by the guests, if any, are their own and do not necessarily represent the views or opinions of Kalkine Media. Some of the images/music that may be used on this website are copyrighted to their respective owner(s). Kalkine Media does not claim ownership of any of the pictures displayed/music used on this website unless stated otherwise. The images/music that may be used on this website are taken from various sources on the internet, including paid subscriptions or are believed to be in public domain. We have made reasonable efforts to accredit the source wherever it was indicated as or found to be necessary.

This disclaimer is subject to change without notice. Users are advised to review this disclaimer periodically for any updates or modifications.

Two ASX Listed Stocks Giving Bullish Indications

Recent Articles

Investing Tips

Previous Next
We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it.