OZ Minerals Limited (ASX: OZL) postponed the target date for the first saleable concentrate production at its Carrapateena prospect from November 2019 to December 2019.
- The miner postponed the concentrate production amid incorrect items supplied by the vendor related to the mineral processing plant, identified by OZL during the commissioning checks.
- OZL now sourced the correct parts and the remediation works are underway.
- Andrew Cole- the current CEO cleared in an announcement that the delay would not hamper the project ramp-up in 2020 amid an advanced state of the underground development.