Rio Tinto and Hancock Prospecting to invest $1.6 billion to develop the Hope Downs 2 project in Western Australia’s Pilbara

June 24, 2025 02:18 PM AEST | By Business Wire
 Rio Tinto and Hancock Prospecting to invest $1.6 billion to develop the Hope Downs 2 project in Western Australia’s Pilbara
Image source: Kalkine Media

PERTH, Australia--(BUSINESS WIRE)--Rio Tinto and Hancock Prospecting will invest $1.61 billion (Rio Tinto share $0.8 billion) to develop the Hope Downs 2 iron ore project in Western Australia’s Pilbara region.

The Hope Downs 2 project, to mine Rio Tinto and Hancock Prospecting’s Hope Downs 2 and Bedded Hilltop deposits, has now received all necessary State and Federal Government approvals.

The two new above-water-table iron ore pits will have a combined total annual production capacity of 31 million tonnes and will sustain production from the Hope Downs Joint Venture into the future.

Rio Tinto Iron Ore Chief Executive Simon Trott said: “Approval of Hope Downs 2 is a key milestone for Rio Tinto, as we invest in the next generation of iron ore mines in the Pilbara.

“These projects are part of our strategy to continue investing in Australian iron ore and to sustain Pilbara production for decades to come, supporting jobs, local businesses and the state and national economies.

“The Pilbara has been critical to global steel supply for more than 60 years, and we are committed to ensuring it remains so well into the future.”

Rio Tinto has engaged with the Nyiyaparli, Banjima and the Ngarlawangga Peoples, along with relevant government stakeholders, to ensure the responsible management of heritage and the environment in development of the project.

The project includes new non-process infrastructure precincts, railway crossings and haul roads, as well as realigning a 6-kilometre section of the Great Northern Highway.

Ore mined at the two sites will be transported to Hope Downs 1 for processing, with first ore from the deposits and associated infrastructure scheduled for 2027.

More than 950 jobs will be created during construction and, once operational, the Hope Downs 2 project will help sustain a workforce of about 1000 full time equivalent roles at Greater Hope Downs.

Hope Downs 2 is part of Rio Tinto’s tranche of replacement projects that underpin the company’s ongoing commitment to the Pilbara, and which will have combined total capacity of about 130Mtpa2.

During the next three years (2025-2027), Rio Tinto expects to invest more than $13 billion on new mines, plant and equipment.

The company has a clear pathway to achieve and sustain mid-term system capacity of 345 to 360Mtpa from its Pilbara iron ore business, with a pre-feasibility study also underway on the Rhodes Ridge project, the Pilbara’s best undeveloped iron ore deposit.

Additional information

Rio Tinto and Hancock Prospecting are equal partners in the Hope Downs Joint Venture.

The Joint Venture was originally established in 2006, with Rio Tinto and Hancock Prospecting's shared history extending back to the early 1960's.

Hope Downs 1 started production in 2007, followed by Hope Downs 4, with first ore in 2013.

Footnotes

1 All currency figures are in US dollars and on a 100 per cent basis, unless otherwise specified. The capital for the project is already included in the Group’s replacement capital guidance.

2 Subject to timing of full capacity. The replacement projects include Western Range which, as previously announced, was opened on 6 June 2025, Brockman Syncline 1, as announced on 6 March 2025, Hope Downs 2, West Angelas and Greater Nammuldi.


Contacts

Please direct all enquiries to [email protected]

Media Relations,
United Kingdom
Matthew Klar
M +44 7796 630 637
David Outhwaite
M +44 7787 597 493

Media Relations,
Australia
Matt Chambers
M +61 433 525 739
Michelle Lee
M +61 458 609 322
Rachel Pupazzoni
M +61 438 875 469

Media Relations,
Canada
Simon Letendre
M +1 514 796 4973
Malika Cherry
M +1 418 592 7293
Vanessa Damha
M +1 514 715 2152

Media Relations,
US
Jesse Riseborough
M +1 202 394 9480

Investor Relations,
United Kingdom
Rachel Arellano
M: +44 7584 609 644
David Ovington
M +44 7920 010 978
Laura Brooks
M +44 7826 942 797
Weiwei Hu
M +44 7825 907 230

Investor Relations,
Australia
Tom Gallop
M +61 439 353 948
Phoebe Lee
M +61 413 557 780

Rio Tinto plc
6 St James’s Square
London SW1Y 4AD
United Kingdom
T +44 20 7781 2000
Registered in England
No. 719885

Rio Tinto Limited
Level 43, 120 Collins Street
Melbourne 3000
Australia
T +61 3 9283 3333
Registered in Australia
ABN 96 004 458 404

This announcement is authorised for release to the market by Andy Hodges, Rio Tinto’s Group Company Secretary.

riotinto.com

Category: Pilbara


Disclaimer

The content, including but not limited to any articles, news, quotes, information, data, text, reports, ratings, opinions, images, photos, graphics, graphs, charts, animations and video (Content) is a service of Kalkine Media Pty Ltd (“Kalkine Media, we or us”), ACN 629 651 672 and is available for personal and non-commercial use only. The principal purpose of the Content is to educate and inform. The Content does not contain or imply any recommendation or opinion intended to influence your financial decisions and must not be relied upon by you as such. Some of the Content on this website may be sponsored/non-sponsored, as applicable, but is NOT a solicitation or recommendation to buy, sell or hold the stocks of the company(s) or engage in any investment activity under discussion. Kalkine Media is neither licensed nor qualified to provide investment advice through this platform. Users should make their own enquiries about any investments and Kalkine Media strongly suggests the users to seek advice from a financial adviser, stockbroker or other professional (including taxation and legal advice), as necessary.
The content published on Kalkine Media also includes feeds sourced from third-party providers. Kalkine does not assert any ownership rights over the content provided by these third-party sources. The inclusion of such feeds on the Website is for informational purposes only. Kalkine does not guarantee the accuracy, completeness, or reliability of the content obtained from third-party feeds. Furthermore, Kalkine Media shall not be held liable for any errors, omissions, or inaccuracies in the content obtained from third-party feeds, nor for any damages or losses arising from the use of such content.
Kalkine Media hereby disclaims any and all the liabilities to any user for any direct, indirect, implied, punitive, special, incidental or other consequential damages arising from any use of the Content on this website, which is provided without warranties. The views expressed in the Content by the guests, if any, are their own and do not necessarily represent the views or opinions of Kalkine Media. Some of the images/music that may be used on this website are copyrighted to their respective owner(s). Kalkine Media does not claim ownership of any of the pictures displayed/music used on this website unless stated otherwise. The images/music that may be used on this website are taken from various sources on the internet, including paid subscriptions or are believed to be in public domain. We have made reasonable efforts to accredit the source wherever it was indicated as or found to be necessary.
This disclaimer is subject to change without notice. Users are advised to review this disclaimer periodically for any updates or modifications.


AU_advertise

Advertise your brand on Kalkine Media

Sponsored Articles


Investing Ideas

Previous Next
We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it.