AEMO takes to the airwaves after meeting no-show

April 17, 2023 07:20 PM PDT | By AAPNEWS
 AEMO takes to the airwaves after meeting no-show
Image source: AAPNEWS

The Australian Energy Market Operator has defended its decision to skip a meeting in western Victoria, where residents and farmers fought becoming a thoroughfare for power lines.

After a convoy of tractors lined the streets of St Arnaud on Monday to protest lines being built on local farms, about 300 people convened in the town hall, but AEMO was notably absent.

Speaking on ABC's Country Hour on Tuesday, AEMO's Victorian planning group manager Nicola Falcon denied the organisation had avoided the big crowd or was trying to control the consultation.

"It was a different format to what we had agreed," Ms Falcon said.

"We want to be able to have productive discussions with a number of different stakeholders." 

She said AEMO aimed to discuss its projects with as many people as possible.

"Consumers want affordable, reliable electricity, and we really do want to be able to explain to as many different people as possible that will help share that low cost," Ms Falcon said.

But the Victoria Energy Policy Centre's Professor Bruce Mountain said the two projects - the Western Renewables Link and the Victoria-to-New South Wales Interconnector West - were seeded from NEMLink, a transmission plan more than a decade old.

"It was written in 2010 at a time when solar was 10 times more expensive than it is now and wind was three times more expensive," Prof Mountain told AAP.

"It had a semblance of credibility because fossil-fuel differences could have justified, to some degree, transmission expansion between states."

Prof Mountain and former Powerlink chief operating officer Simon Bartlett's submission on the project says the grid would be better served by building on existing infrastructure in Gippsland, the heart of Victorian energy production for more than half a century.

"We've got all these circuits that have got masses of spare capacity on them,'' he said.

"They can be augmented easily because there's easements that can be upgraded from 220kV to 500kV."

Prof Mountain said AEMO's project viability models had made transmission in Gippsland seem more expensive than it was, while bolstering the perceived benefit of the western Victorian projects.

"It will be built over five to eight years, and when it's complete transmission charges will double," he said.

"And it will double for so little additional transmission capability."

The Victorian government has defended the project, AEMO and its consultation.

"AEMO have consulted with communities and experts on the design of these transmission projects and will continue to engage as the projects progress, ensuring they deliver benefits for both local communities and energy consumers," a spokeswoman said.

"New transmission is vital for securing clean, affordable power for every Victorian town, and enabling the development of our renewable energy industry as we work towards net-zero emissions by 2045." 


Disclaimer

The content, including but not limited to any articles, news, quotes, information, data, text, reports, ratings, opinions, images, photos, graphics, graphs, charts, animations, and video (Content) is a service of Kalkine Media LLC., having Delaware File No. 4697309 (“Kalkine Media, we or us”) and is available for personal and non-commercial use only. The principal purpose of the Content is to educate and inform. The Content does not contain or imply any recommendation or opinion intended to influence your financial decisions and must not be relied upon by you as such. Some of the Content on this website may be sponsored/non-sponsored, as applicable, but is NOT a solicitation or recommendation to buy, sell or hold the stocks of the company(s) or engage in any investment activity under discussion. Kalkine Media is neither licensed nor qualified to provide investment advice through this platform. Users should make their own enquiries about any investments and Kalkine Media strongly suggests the users to seek advice from a financial adviser, stockbroker or other professional (including taxation and legal advice), as necessary. Kalkine Media hereby disclaims any and all the liabilities to any user for any direct, indirect, implied, punitive, special, incidental or other consequential damages arising from any use of the Content on this website, which is provided without warranties. The views expressed in the Content by the guests, if any, are their own and do not necessarily represent the views or opinions of Kalkine Media.
The content published on Kalkine Media also includes feeds sourced from third-party providers. Kalkine does not assert any ownership rights over the content provided by these third-party sources. The inclusion of such feeds on the Website is for informational purposes only. Kalkine does not guarantee the accuracy, completeness, or reliability of the content obtained from third-party feeds. Furthermore, Kalkine Media shall not be held liable for any errors, omissions, or inaccuracies in the content obtained from third-party feeds, nor for any damages or losses arising from the use of such content. Some of the images/music that may be used on this website are copyrighted to their respective owner(s). Kalkine Media does not claim ownership of any of the pictures/music displayed/used on this website unless stated otherwise. The images/music that may be used on this website are taken from various sources on the internet, including paid subscriptions or are believed to be in public domain. We have used reasonable efforts to accredit the source (public domain/CC0 status) to where it was found and indicated it, as necessary.
This disclaimer is subject to change without notice. Users are advised to review this disclaimer periodically for any updates or modifications.


Sponsored Articles


Investing Ideas

Previous Next