HS2: What is it, how much has it cost and how have the plans changed?

September 24, 2023 11:12 AM AEST | By PAMEDIA
Follow us on Google News:

The Prime Minister is reportedly considering axing plans for the HS2 high-speed rail link to run from Birmingham to Manchester amid soaring costs.

Critics of such a move include former prime ministers Boris Johnson, some business leaders and Labour mayors of Greater Manchester and London, Andy Burnham and Sadiq Khan.

But Chancellor Jeremy Hunt has suggested the scheme is “out of control” and former transport secretary Grant Shapps said the Government could not write an “open-ended cheque” if costs continue to rise.

HS2 network
(PA Graphics)

A decision on the fate of the project’s Manchester leg is expected in the coming days.

Here, the PA news agency explains what HS2 is, looks at the costs involved and how plans have changed.

– What is HS2?

A project for a high-speed rail line linking some of the country’s largest cities, intended to connect London, the Midlands and the north of England, with construction split into three phases.

Gordon Brown’s Labour government set up HS2 Ltd in 2009 and the project has been backed by successive Conservative governments since 2010.

In 2020, then premier Mr Johnson recommitted his Government to the scheme following a review.

– What has it cost so far?

In 2013, HS2 was estimated to cost £37.5 billion in 2009 prices but the sums have continued to spiral.

A budget of £55.7 billion for the whole of HS2 was set in 2015 but some reports suggest costs have now surpassed £100 billion, having been driven up by recent inflation rises.

– What were the original plans?

Phase 1: London Euston to Birmingham Curzon Street, with intermediate stations at Old Oak Common in the western suburbs and at Birmingham Airport.

HS2 network changes
(PA Graphics)

Phase 2A: To extend the line from Fradley in the West Midlands to Crewe in Cheshire.

Phase 2B: Comprised of an eastern leg from the West Midlands to the East Midlands and a western leg from Crewe to Manchester.

– How have the ambitions shrunk?

Ministers have already moved to pause parts of the project and even axed sections in the north.

The eastern leg between Birmingham and Leeds was reduced to a spur line which is due to end in the East Midlands.

It was confirmed in March that construction between Birmingham and Crewe would be delayed by two years and that services may not enter central London until the 2040s.

A concept drawing for Old Oak Common Station in west London
A concept drawing for Old Oak Common Station in west London (HS2/PA)

Transport Secretary Mark Harper announced that work at Euston would be paused for two years as costs were forecast to almost double to £4.8 billion.

The pause means Old Oak Common, in the capital’s western suburbs, will be the railway’s only London station when services to and from Birmingham Curzon Street begin between 2029 and 2033.

The Prime Minister is reportedly now considering scrapping the route from Birmingham to Manchester, with a decision on the fate of the leg north from Birmingham is expected within days.


Disclaimer

The content, including but not limited to any articles, news, quotes, information, data, text, reports, ratings, opinions, images, photos, graphics, graphs, charts, animations and video (Content) is a service of Kalkine Media Pty Ltd (Kalkine Media, we or us), ACN 629 651 672 and is available for personal and non-commercial use only. The principal purpose of the Content is to educate and inform. The Content does not contain or imply any recommendation or opinion intended to influence your financial decisions and must not be relied upon by you as such. Some of the Content on this website may be sponsored/non-sponsored, as applicable, but is NOT a solicitation or recommendation to buy, sell or hold the stocks of the company(s) or engage in any investment activity under discussion. Kalkine Media is neither licensed nor qualified to provide investment advice through this platform. Users should make their own enquiries about any investments and Kalkine Media strongly suggests the users to seek advice from a financial adviser, stockbroker or other professional (including taxation and legal advice), as necessary. Kalkine Media hereby disclaims any and all the liabilities to any user for any direct, indirect, implied, punitive, special, incidental or other consequential damages arising from any use of the Content on this website, which is provided without warranties. The views expressed in the Content by the guests, if any, are their own and do not necessarily represent the views or opinions of Kalkine Media. Some of the images/music that may be used on this website are copyright to their respective owner(s). Kalkine Media does not claim ownership of any of the pictures displayed/music used on this website unless stated otherwise. The images/music that may be used on this website are taken from various sources on the internet, including paid subscriptions or are believed to be in public domain. We have used reasonable efforts to accredit the source wherever it was indicated as or found to be necessary.



Top ASX Listed Companies

We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it. OK