SAINT-PAUL-LEZ-DURANCE, FRANCE, April 30, 2025 /EINPresswire.com/ -- In a landmark achievement for fusion energy, ITER has completed all components for the world’s largest, most powerful pulsed superconducting electromagnet system.

ITER is an international collaboration of more than 30 countries to demonstrate the viability of fusion—the power of the sun and stars—as an abundant, safe, carbon-free energy source for the planet.

The final component was the sixth module of the Central Solenoid, built and tested in the United States. When it is assembled at the ITER site in Southern France, the Central Solenoid will be the system’s most powerful magnet, strong enough to lift an aircraft carrier.

The Central Solenoid will work in tandem with six ring-shaped Poloidal Field (PF) magnets, built and delivered by Russia, Europe, and China.

The fully assembled pulsed magnet system will weigh nearly 3,000 tons. It will function as the electromagnetic heart of ITER’s donut-shaped reactor, called a Tokamak.

How does this pulsed superconducting electromagnet system work?
Step 1. A few grams of hydrogen fuel—deuterium and tritium gas—are injected into ITER’s gigantic Tokamak chamber.
Step 2. The pulsed magnet system sends an electrical current to ionize the hydrogen gas, creating a plasma, a cloud of charged particles.
Step 3. The magnets create an “invisible cage” that confines and shapes the ionized plasma.
Step 4. External heating systems raise the plasma temperature to 150 million degrees Celsius, ten times hotter than the core of the sun.
Step 5. At this temperature, the atomic nuclei of plasma particles combine and fuse, releasing massive heat energy.

At full operation, ITER is expected to produce 500 megawatts of fusion power from only 50 megawatts of input heating power, a tenfold gain. At this level of efficiency, the fusion reaction largely self-heats, becoming a “burning plasma.”

By integrating all the systems needed for fusion at industrial scale, ITER is serving as a massive, complex research laboratory for its 30-plus member countries, providing the knowledge and data needed to optimize commercial fusion power.

ITER’s geopolitical achievement is also remarkable: the sustained collaboration of ITER’s seven members—China, Europe, India, Japan, Korea, Russia, and the United States. Thousands of scientists and engineers have contributed components from hundreds of factories on three continents to build a single machine.

Pietro Barabaschi, ITER Director-General, says, “What makes ITER unique is not only its technical complexity but the framework of international cooperation that has sustained it through changing political landscapes.”

“This achievement proves that when humanity faces existential challenges like climate change and energy security, we can overcome national differences to advance solutions.”

“The ITER Project is the embodiment of hope. With ITER, we show that a sustainable energy future and a peaceful path forward are possible.”

In 2024, ITER reached 100% of its construction targets. With most of the major components delivered, the ITER Tokamak is now in assembly phase. In April 2025, the first vacuum vessel sector module was inserted into the Tokamak Pit, about 3 weeks ahead of schedule.

The past five years have witnessed a surge in private sector investment in fusion energy R&D. In November 2023, the ITER Council recognized the value and opportunity represented by this trend.

They encouraged the ITER Organization and its Domestic Agencies to actively engage with the private sector, to transfer ITER’s accumulated knowledge to accelerate progress toward making fusion a reality.

In 2024, ITER launched a private sector fusion engagement project, with multiple channels for sharing knowledge, documentation, data, and expertise, as well as collaboration on R&D. This tech transfer initiative includes sharing information on ITER’s global fusion supply chain, another way to return value to Member governments and their companies.

In April 2025, ITER hosted a public-private workshop to collaborate on the best technological innovation to solve fusion’s remaining challenges.

The ITER experiment under construction in southern France. The tokamak building is the mirrored structure at center. Courtesy ITER Organization/EJF Riche.

Under the ITER Agreement, Members contribute most of the cost of building ITER in the form of building and supplying components. This arrangement means financing from each Member goes primarily to their own companies, to manufacture ITER’s challenging technology. In doing so, these companies also drive innovation and gain expertise, creating a global fusion supply chain.

Europe, as Host Member, contributes 45% of the cost of the ITER Tokamak and its support systems. China, India, Japan, Korea, Russia, and the USA each contribute 9%, but all Members get access to 100% of the intellectual property.

The United States has
* Built the Central Solenoid, made of six modules, plus a spare.
* Delivered the “exoskeleton” support structure (comprised of 9,000+ individual parts manufactured by eight U.S. suppliers) that will enable the Central Solenoid to withstand the extreme forces it will generate.
* Fabricated about 8% of the Niobium-Tin (Nb3Sn) superconductors used in ITER’s Toroidal Field magnets.

Russia has
* Delivered the 9-meter-diameter ring-shaped Poloidal Field magnet that will crown the top of the ITER Tokamak.
* Working closely with Europe, produced approximately 120 tonnes of Niobium-Titanium (NbTi) superconductors, comprising about 40% of the total required for ITER’s Poloidal Field magnets.
* Manufactured giant busbars that will deliver power to the magnets at the required voltage and amperage, as well as the upper port plugs for ITER’s vacuum vessel sectors.

Europe has
* Manufactured four of the ring-shaped Poloidal Field magnets onsite in France, ranging from 17 to 24 meters in diameter.
* Delivered 10 of ITER’s Toroidal Field magnets and produced a substantial portion of the Niobium-Tin (Nb3Sn) superconductors used in these TF magnets.
* and as creating five of the nine sectors of the Tokamak vacuum vessel, the donut-shaped chamber where fusion will take place.

China, under an arrangement with Europe, has
* Manufactured a 10-metre Poloidal Field magnet, already installed at the bottom of the partially assembled ITER Tokamak.
* Contributed the NbTi superconductors for PF magnets 2, 3, 4, and 5, about 65% of the PF magnet, andabout 8% of the Toroidal Field magnet superconductors.

News release in full: https://conta.cc/3ErV2tl

Terry Collins
Terry Collins & Assoc. inc
+1 416-878-8712
email us here

Legal Disclaimer:

EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.


Disclaimer

The content, including but not limited to any articles, news, quotes, information, data, text, reports, ratings, opinions, images, photos, graphics, graphs, charts, animations and video (Content) is a service of Kalkine Media Limited, Company No. 12643132 (“Kalkine Media, we or us”) and is available for personal and non-commercial use only. Kalkine Media is an appointed representative of Kalkine Limited, who is authorized and regulated by the FCA (FRN: 579414). The non-personalized advice given by Kalkine Media through its Content does not in any way endorse or recommend individuals, investment products or services suitable for your personal financial situation. You should discuss your portfolios and the risk tolerance level appropriate for your personal financial situation, with a qualified financial planner and/or adviser. No liability is accepted by Kalkine Media or Kalkine Limited and/or any of its employees/officers, for any investment loss, or any other loss or detriment experienced by you for any investment decision, whether consequent to, or in any way related to this Content, the provision of which is a regulated activity. Kalkine Media does not intend to exclude any liability which is not permitted to be excluded under applicable law or regulation. Some of the Content on this website may be sponsored/non-sponsored, as applicable. However, on the date of publication of any such Content, none of the employees and/or associates of Kalkine Media hold positions in any of the stocks covered by Kalkine Media through its Content. The views expressed in the Content by the guests, if any, are their own and do not necessarily represent the views or opinions of Kalkine Media.
The content published on Kalkine Media also includes feeds sourced from third-party providers. Kalkine does not assert any ownership rights over the content provided by these third-party sources. The inclusion of such feeds on the Website is for informational purposes only. Kalkine does not guarantee the accuracy, completeness, or reliability of the content obtained from third-party feeds. Furthermore, Kalkine Media shall not be held liable for any errors, omissions, or inaccuracies in the content obtained from third-party feeds, nor for any damages or losses arising from the use of such content. Some of the images/music/video that may be used in the Content are copyright to their respective owner(s). Kalkine Media does not claim ownership of any of the pictures displayed/music or video used in the Content unless stated otherwise. The images/music/video that may be used in the Content are taken from various sources on the internet, including paid subscriptions or are believed to be in public domain. We have used reasonable efforts to accredit the source wherever it was indicated or was found to be necessary.
This disclaimer is subject to change without notice. Users are advised to review this disclaimer periodically for any updates or modifications.


Sponsored Articles