Cyprium Metals advancing towards refurbishment of its Nifty Copper Project - Kalkine Media

September 29, 2022 11:15 AM AEST | By Team Kalkine Media
Follow us on Google News: https://kalkinemedia.com/resources/assets/public/images/google-news.webp

Highlights

  • Cyprium Metals is consistently stepping closer to the process of refurbishment of its Nifty Copper Project.
  • Most activities pertaining to operational readiness and environmental clean-up are about to complete.
  • Also, the company is advancing discussions with multiple parties to raise funds for the restart of the Nifty Copper Project.

ASX copper player, Cyprium Metals Limited (ASX:CYM) continues to further the refurbishment of its Nifty Copper Project along with making arrangement for a finance process for restarting the operation. The company has carried forward the predevelopment work to ensure that the Nifty site was ready at the go-line upon completion of financing, before refurbishment and construction activities are initiated.

As per the company Nifty employees have made excellent progress thus far, especially when comes to being operational ready for the project kickoff. The site has remained on care and maintenance ever since its acquisition. This has been achieved by Nifty for the last 14 months, that too without any lost time injury

A quick look at the progress made so far

·        Collection ponds and heaps set for success

The process of trenching and drilling was conducted around the heap leach pads to collect samples for assays and testing. Also, drainage was restored, as leach solutions were required to be channelised to the collection ponds. This will also prevent overflowing in case of rain. Access too has been reestablished to the top of the heap for transporting and placing residue from the collection ponds. As needed, steps were taken to direct the solution from the heap to drains at the heap front.

The collection ponds have filled up with residue, in turn reducing storage freeboard. Access has been established to dry out the ponds and excavate material back to the heap leach when required. Upon emptying, the ponds can be surveyed, repaired, and relined.

Leach Solution pumped from collection ponds to PLS pond – blue copper sulphate solution

Source: Company announcement

·        Capacity enhancement

Alongside, the company has also upgraded the capacity of the ponds to retain the solution within the ponds during rainfall, which was restricted in the past because of being filled up with solids. The solution has a grade of +10 gpl copper versus a usual solvent extraction (SX) feed grade of 3 to 4 gpl. This substantial solution inventory of more than 500 tonnes of copper is available for project commissioning.

·        Cleanup activity

The SX has been cleaned up to the extent of being ready for refurbishment tasks. The electrowinning (EW) cleanup has progressed with stripping of anodes and cathodes from cells. Several cathodes had copper attached which has been stripped and placed on pallets for sale. Currently, the pallets have about 25 tonnes of copper cathode. The tanks contain dropped anode and cathode along with dried copper sulphate at the base.

The cathodes and anodes have been palleted up for sale because of their recycling value for stainless steel, lead and copper. The dried solids have been collected to return to the circuit until refurbishment commissioning. Upon removal of the solids, the pipework will be taken out for tank cleaning. Following this, the tanks are filled and hydrotested to check leakage. Then, the tanks are emptied for reline and leak repair once refurbishment starts.

EW cells stripped of anodes and cathodes, cleaned and hydrotested waiting for refurbishment

Source: Company announcement

·        Fixed infrastructure development

A review of fixed infrastructure was done to assess it for refurbishment when the construction starts. Refurbishment of camp accommodation, and significant data communications infrastructure upgrades are being made to bring them up to standard ready for commencement of construction activities.

Talks on for project financing

Cyprium has been making persistent efforts to arrange finances for its Nifty Copper Project. It is aiming a value between AU$240 million to AU$260 million as a debt funding package. The proceeds once obtained will be directed to finance the restart process at Nifty and other project costs. This is likely to comprise subordinated debt, senior secured financing, and offtake financing.

Positive discussions and negotiation of terms are underway with multiple parties.

Management Commentary

Image: © 2022 Kalkine Media®

CYM stock last traded at AU$0.069 on 29 September 2022.


Disclaimer

The content, including but not limited to any articles, news, quotes, information, data, text, reports, ratings, opinions, images, photos, graphics, graphs, charts, animations and video (Content) is a service of Kalkine Media Pty Ltd (Kalkine Media, we or us), ACN 629 651 672 and is available for personal and non-commercial use only. The principal purpose of the Content is to educate and inform. The Content does not contain or imply any recommendation or opinion intended to influence your financial decisions and must not be relied upon by you as such. Some of the Content on this website may be sponsored/non-sponsored, as applicable, but is NOT a solicitation or recommendation to buy, sell or hold the stocks of the company(s) or engage in any investment activity under discussion. Kalkine Media is neither licensed nor qualified to provide investment advice through this platform. Users should make their own enquiries about any investments and Kalkine Media strongly suggests the users to seek advice from a financial adviser, stockbroker or other professional (including taxation and legal advice), as necessary. Kalkine Media hereby disclaims any and all the liabilities to any user for any direct, indirect, implied, punitive, special, incidental or other consequential damages arising from any use of the Content on this website, which is provided without warranties. The views expressed in the Content by the guests, if any, are their own and do not necessarily represent the views or opinions of Kalkine Media. Some of the images/music that may be used on this website are copyright to their respective owner(s). Kalkine Media does not claim ownership of any of the pictures displayed/music used on this website unless stated otherwise. The images/music that may be used on this website are taken from various sources on the internet, including paid subscriptions or are believed to be in public domain. We have used reasonable efforts to accredit the source wherever it was indicated as or found to be necessary.

5 ASX Companies Leveraging AI to Drive Growth in 2024



We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it.